UAE-based Azizi Developments has announced that works on Park Avenue II, a mixed-use project in Dubai’s MBR City, are 90% complete, with handover scheduled for the third quarter.
Park Avenue is a vibrant and convenient senior residential community consisting of three buildings with a total of 372 residences and 29 retail units, each with a well-equipped gym and swimming pool.
Aziz said that the project is advancing at full speed. The structure, blocks and internal plastering of the second phase of Park Avenue have been 100% completed, and the manpower of all buildings on Park Avenue has reached 529.
Tiling, HVAC, and MEP work are currently 95%, 97% and 95% complete respectively, while exterior work is 76% complete. The swimming pool is 82% complete, while the facade is 96% complete. It added that the overall completion rate is currently 80%.
“We are excited about Park Avenue II’s remarkable progress and eagerly look forward to its on-schedule completion in the third quarter of 2023,” said CEO Farhad Azizi.
“Through our rigorous selection of high-quality building materials and hiring only reliable contractors, we have accelerated construction and further enhanced the quality of the project, meeting and even exceeding the expectations of our valued investors and end users,” he said.
“Park Avenue II will offer residents an unparalleled lifestyle experience. We are very excited to welcome hundreds of happy families into their new homes in the coming months,” he added.- Trade Arab News Agency